A solar-only retrofit skips the Town's offset; snowmelt or a spa brings it in
If you are only adding panels to an existing home, the Town's exterior energy offset does not apply to you. It applies when a permitted project adds snowmelt beyond the exempt area, a site-built pool or spa, or a factory spa above the standby limit. Then panels on your own property count double toward the offset, but they stay tied to the property for life. Either way, San Miguel Power Association (SMPA), the co-op that supplies power here, fully net meters a home system only up to 10 kW. Net metering means power you send to the grid earns a credit against power you draw later; a kilowatt (kW) is a system's rated size.
What the offset rule covers
Mountain Village's building code (MVMC 17.7, section 17.7.12, the Town's energy code amendments) says the energy used by exterior snowmelt, site-built pools and spas "must also be offset with renewable energy." The code calls this the Offset Program; the Town's fee schedule lists its charges as REMP fees, which is the name most local quotes will use. Some snowmelt is exempt:
| Property | Exempt snowmelt |
|---|---|
| Single-family home | 1,000 sq ft of hydronic snowmelt on the main drive and required exit walkways, decks, stairs and landings |
| Duplex or townhome | 500 sq ft per unit |
| Multifamily, mixed-use, commercial | 1,000 sq ft plus 50 sq ft per unit |
A factory-built spa that meets California Energy Commission rules, with standby use at or below 205 watts, is exempt; above that, its standby use counts. For anything beyond the exemptions, the owner chooses one of three options:
- Renewable energy from a Town-approved system. On-site systems get double credit: the code's example says a system that "produces 4KW" gets credit "for offsetting 8KW" of exterior energy use.
- Payment in lieu, a fee paid to the Town instead, due before the building permit for that project is issued.
- A mix of both, part panels and part payment.
The strings attached
The Building Official must approve on-site offset systems in advance and may require engineering at the owner's expense. They must be "maintained and operated for the lifetime of the property," through a written agreement and a covenant, a restriction recorded against the property that binds later owners. Panels you install for the offset cannot simply be removed later, and the obligation passes to whoever buys the house.
The Building Official calculates the offset with the Town's Build Smart spreadsheet. The copy linked from the Building Division page is password-protected, so its snowmelt and spa rates, and the payment-in-lieu rate, could not be checked for this page. The code's "4KW … 8KW" example also mixes power and energy units. Before you sign, ask the Building Division for a sample calculation for your snowmelt area or spa, and ask whether the double credit is counted in rated kilowatts or in yearly kilowatt-hours.
A caution for homes with gas snowmelt
Our interpretation, not a Town or SMPA ruling: the offset counts exterior energy whether your snowmelt boiler burns gas or runs on electricity, while SMPA's policy treats a home system as offsetting the electric use at that location. On a house with gas snowmelt, panels added for offset credit can push yearly output past what the house uses in electricity. That surplus is paid only at SMPA's avoided cost (explained below). A good plan shows both totals side by side.
Worked example: 6 kW for the house plus 4 kW for the offset fills the 10 kW limit
Illustrative example. A detached home plans a remodel that adds heated walkways beyond the 1,000 sq ft exemption, plus a site-built spa. Suppose the Building Official's spreadsheet says the extra exterior energy needs an offset equal to 8 kW of renewable output. With double credit, 4 kW of on-site solar covers it. The household's own electric use calls for about 6 kW.
Group Size Covenant? SMPA total after this phase Phase 1: house load 6 kW No 6 kW Phase 1: offset group 4 kW Yes, for the life of the property 10 kW Phase 2: reserve (dashed on the map) 3 kW No 13 kW Phase 1 lands at exactly SMPA's 10 kW residential net-metering limit. Phase 2 takes the system to 13 kW, so it needs a split system or net billing, and the added output earns avoided cost, not the retail rate. The 8 kW requirement and 6 kW house load are invented; the example assumes the Town counts credit in rated kilowatts, as its code example does.
Order matters here. A phase 1 that looks sensible on its own uses the whole 10 kW, so "add later" arrives with worse credit terms. There are three ways to keep room:
- Pay part of the offset in lieu. Build 2 kW of offset panels and pay the Town for the rest. Phase 1 becomes 8 kW, leaving 2 kW of fully net-metered room. Whether that beats panels depends on the payment-in-lieu rate, so ask for both figures.
- Make phase 2 a battery. The panel total stays at 10 kW, and the battery targets SMPA's evening rate (next section). Ask SMPA first how a battery is treated in your agreement.
- Accept split metering for phase 2 knowingly, with avoided-cost credit priced into the phase 2 estimate.
Whichever you choose, draw the offset panels as their own labeled group, so a future buyer knows which ones carry the covenant.
SMPA credits the first 10 kW in two banks
SMPA's service-area page lists Mountain Village, and the Town calls SMPA the sole electricity provider to the Telluride region. A kilowatt-hour (kWh) is energy made or used over time; the banks and credits below are counted in kWh.
Under SMPA's Net Metering Policy 303 (revised January 25, 2022, still linked from SMPA's site in November 2026):
- Residential net metering covers systems of 10 kW or less.
- From 10 kW up to 100 kW, you choose a split system (the part above 10 kW on a second production meter, with a new account and its own monthly access charge) or net billing (monthly excess credited at a lower rate instead of carried forward). Both pay the Net Meter Avoided Cost, the rate SMPA sets for power it would otherwise buy. Its current value was not published on the SMPA pages checked; ask SMPA.
- Monthly excess carries forward one-for-one. The leftover is settled at avoided cost once a year on a true-up date, April 1 or November 1 (a one-time choice), and paid within 60 days.
- Liability insurance of $300,000 is required for systems up to 25 kW, and the member pays interconnection costs.
- Renewable energy credits (RECs), the certificates for the "green" value of your output, go to SMPA.
Ask SMPA whether a newer revision of the policy exists.
Our reading of Policy 303 for snowmelt homes: if your snowmelt is electric, the true-up date matters more than usual. An April 1 date keeps summer credits banked through the snowmelt season. A November 1 date settles them at avoided cost just before the heaviest electric use of the year.
The two banks, and why phase 2 might be a battery
SMPA's net metering page lists the default time-of-use rate (current rates, November 2026): a $33 monthly access fee, $0.25 per kWh on-peak (4 to 9 p.m.) and $0.11 off-peak. Net-metered accounts on that rate have two kWh banks, and "KWh credits will not transfer between banks."
Illustrative example. A kWh your roof exports at 1 p.m. lands in the off-peak bank, worth $0.11. A kWh the house draws at 6 p.m. costs $0.25 and can only be paid from the on-peak bank. If phase 1 makes 600 kWh more off-peak than the house uses off-peak in July, those credits roll forward and are settled at avoided cost at true-up. (The 600 kWh is invented.)
Solar makes little power from 4 to 9 p.m., least of all in winter. That argues for a battery as a later phase, or for checking SMPA's optional Time-of-Day Peak Power rate ($35 a month, $0.1196 per kWh, $3.50 per kW of 4 to 9 p.m. peak demand, one bank for all excess), before adding more off-peak panels. It also matters for the offset group: its output lands mostly in the off-peak bank, like the rest of the array.
If your property sits on the Telluride side of the town line, the Telluride page covers the same co-op terms with Telluride's own permits and historic review. Mountain Village's offset rule does not apply there.
File with the Town first, then SMPA's three steps
The Town of Mountain Village is the "sole Authority Having Jurisdiction" here: the AHJ that issues building and electrical permits and inspects the work. A private solar system is a permitted use in the single-family, multifamily and Village Center zones, so the questions are about filings and review, not zoning use. The order:
- Installer registration and the approved list. The Town's Building Division requires contractors to complete a Contractor Registration in OpenGov, the Town's permit portal, before submitting any permit. Electrical contractors need state licenses plus Town registration. The Town's solar pages add that installers "must be on the Town's approved, licensed contractors list." The list linked there dates from 2024, so ask whether it has been updated.
- Ask about design review. The 2025 fee schedule lists a "Renewable Energy System Only Application" as Class 3, Design Review Board (DRB) level, with "No Fee as incentive." None of the ten sets of 2026 DRB minutes (January to October) mentions solar, so a flush rooftop array may be handled by staff. Ask Planning whether yours needs review, and at which class, before you sign. The DRB meets the first Thursday of most months, so a review can add weeks.
- Solar permit in OpenGov. The Town's Solar Energy page commits to a solar-specific application and to processing complete small rooftop PV permits in three business days. The 2025 community development fee schedule sets the residential solar permit at $500. Ask whether Town and county use tax apply on top, and whether a 2026 schedule has replaced it. If the same project carries an offset payment in lieu, it is due before that building permit issues.
- Town inspections. A solar inspection "before cover" (the installer requests it and provides a ladder), then a final electrical inspection.
- SMPA Step 1. The contractor applies with a PVWatts estimate (the free federal production calculator). SMPA models your circuit, which "may take a few weeks," so file alongside the Town permit.
- SMPA Step 2. After the Town's electrical inspection passes, the contractor submits the as-built one-line, a wiring diagram of the system as actually installed.
- SMPA Step 3. You sign the Net Metering Agreement and SMPA gives permission to operate (PTO). Credit starts here, not when the panels went up.
Every phase repeats the route: a new OpenGov permit, new Town inspections, new SMPA Steps 1 to 3. Price phase 2's paperwork into the plan now, not when you are ready to build it.
Design for 130 psf, 90 mph and −15°F, and say where snow lands
Mountain Village sits at about 9,500 feet (USGS elevation data), and the Town writes its own climate values into chapter 17.7:
- Ground snow load: 130 pounds per square foot (psf) minimum, plus an elevation adjustment per the Structural Engineers Association of Colorado guide. Ground snow load is the snow weight a structure is designed around, before roof factors.
- Wind: 90 mph three-second gust, exposure C.
- Winter design temperature: −15°F.
These values sit in the Town's amendments to the International Building Code; houses are built under the residential code. Ask the installer to state in writing the snow value the plan reviewer accepted for your house, and to show the racking and roof attachments are rated for it.
The −15°F value matters for wiring. Panels make higher voltage when cold, and the string voltage check (a string is panels wired in series to one inverter input) uses the coldest expected temperature to keep each string under the inverter's limit. That decides whether phase 2 can join an existing string or needs its own inverter input. Ask which temperature the calculation used.
Where the snow goes
The Town's development code requires site plans to include "a snow shed and storage plan for roofs, walkways and drives." A layout should show where each group sheds: onto a door, a deck, the drive, a meter, the hot tub.
For multifamily and mixed-use buildings, including the Village Center, roofs must not shed snow or ice onto public areas, plazas, sidewalks or rights-of-way, and retention must be designed and stamped by an engineer or roofing professional. That rule limits where a condo building can carry panels. If you own a unit, get the association's solar rules in writing before requesting quotes.
Solar roof tiles, instead of racked panels, need a specific DRB Class 3 approval outside the Village Center.
Check the price per watt, then subtract only what applies
"Why are solar installers so expensive?" has a partly local answer here: racking for 130 psf and more, snow guards, travel, and Town and SMPA paperwork for each phase. A price per watt ($/W) check shows how much of a quote those explain.
Illustrative calculation. A phase 1 quote lists $24,600 for 6.0 kW DC, including snow guards ($900) and phase 2 readiness items, upsized conduit and spare rail ($1,100). Solar-only price: $24,600 − $900 − $1,100 = $22,600. Divide by 6,000 watts: $3.77/W, about 25% above the State benchmark of $3.02/W on EcoGen's Colorado cost of solar panels page (Solar Cost Index, September 2026 Edition, prices as of September 25, 2026; cash, homeowner-owned, solar only, before incentives). Subtract SMPA's $300 and, if funds remain, the Town's $2,500: net $21,800. (Quote figures are invented.)
How to use the result:
- Separate first. EcoGen's solar database method warns against comparing a solar-only cash benchmark with a quote that includes a battery or financing. Take out snow guards, readiness items (work done now so phase 2 is cheaper later: larger conduit, extra rail, breaker space, a bigger inverter), any battery and any finance charge.
- Treat the gap as questions, not a verdict. Ask the installer to explain the difference line by line: snow-rated racking, roof type, travel, and the Town and SMPA steps. A statewide average does not price a 130 psf roof at 9,500 feet.
- Don't treat "$0 down" as a price. It describes financing; ask for the total cost of the loan or lease.
- Price the offset group separately if your project has one, next to the payment-in-lieu figure for the same share of the offset.
The incentives that actually remain
- SMPA rebate: $0.10 per watt, up to 3 kW or $300, filed by the contractor; deadlines apply (SMPA renewable rebates).
- Town rebate: $2,500, plus $2,500 more for deed-restricted properties, and battery rebates of $1,000 under 19.9 kWh or $2,000 at 20 kWh and over. First come, first served until funds run out; apply after installation (Town solar incentive). Confirm funds remain, and ask whether phase 2, or a phase 2 battery, could qualify separately.
- No federal credit. The Town's incentive page still mentions a 30% federal credit, but the IRS says the residential clean energy credit "is not available for any property placed in service after December 31, 2025."
How "start small, add later" would work in Mountain Village
Solar Today and Tomorrow is a proposed service for mountain homes: a first phase that fits today's budget and the utility's limit, built so phase 2 is cheap to add. Coverage of Mountain Village is proposed and not yet confirmed. The home page explains the phased method in general; here it would be fitted to SMPA's 10 kW limit and the Town's offset rule.
The written deliverables would be (Proposed service):
- Phase map. Three groups on the roof: house load, the offset group marked as covenanted (if your project triggers the offset), and the phase 2 reserve dashed.
- Cap sheet. SMPA's total after each phase against 10 kW, the expected split between the two banks, and your yearly electric use beside the offset group's output.
- Snow sheet. Where each group sheds (doors, decks, drives, plazas), snow guards, the racking rating against the Town's design values, and the clearing path.
- Readiness items on their own lines, so you can drop any of them.
- Phase 2 paperwork list. New OpenGov permit, new SMPA Step 1, and whether a second Town rebate is possible.
Phase 2 would get a written trigger: your budget; snowmelt or a spa you plan to add; or a battery, when your evening bank shows more panels would mostly add off-peak credit.
Mountain Village quote checklist
The quote checklist on this site covers the same ground; each line here maps to a rule above.
Installer and route
- Is the installer on the Town's approved list and registered in OpenGov? Ask to see both.
- Does the quote show the $500 permit and any use tax as separate lines?
- What did Planning say about design review? Get it in writing.
The offset (if snowmelt, a spa or a pool is planned)
- Does the project trigger it? Show the exempt area used.
- A sample spreadsheet calculation, and how the double credit was counted.
- Which panels carry the covenant, drawn as their own group.
- The payment-in-lieu figure, full and partial, for comparison.
- Is the snowmelt gas or electric? With gas: electric use and offset output side by side.
SMPA terms
- SMPA's total after each phase, against 10 kW.
- Over 10 kW: split system or net billing, and the avoided-cost value assumed.
- True-up date choice, insurance and interconnection costs.
- The Step 1 PVWatts estimate, with monthly figures.
- Who submits the as-built one-line, and the expected PTO date.
Design and price
- Accepted snow value, racking rating, wind value and string-voltage temperature.
- The snow sheet, including plazas or walkways for a shared building.
- Guards, readiness items, battery and financing on separate lines, plus the solar-only $/W.
- Who files the SMPA rebate, and whether Town funds remain.
Compare at least two quotes line by line against this list.
Short answers
Does Colorado have a tax credit for solar panels? Not a federal one: the IRS ended the residential clean energy credit for property placed in service after 2025. Here, check SMPA's rebate (up to $300) and the Town's ($2,500 while funds last).
Why do solar installers cost more here? Partly local reasons: racking for at least 130 psf of ground snow, snow guards, travel, and a Town permit plus an SMPA application for each phase. Run the $/W check and ask for the gap to $3.02/W line by line.
Can I add panels later? Yes, but each phase repeats the Town permit and SMPA's three steps, and capacity past 10 kW earns avoided cost. Plan for it in phase 1.
I own a condo. Can I go solar? Possibly. Association rules apply, and multifamily roofs may not shed onto public areas. Ask the association for its solar rules first.